top of page

DEFENSE SUPPLY CENTER BUILDINGS 41 & 42

- Columbus, OH -

DefenseLogisticsAgency.png

PROJECT CLIENT

Defense Logistics Agency

PROJECT VALUE

$2,266,285

PROJECT SIZE

750,000 sq. ft.

PROJECT COMPLETION

September 2010

PROJECT DESCRIPTION

Buildings 41 and 42 at the Defense Supply Center Columbus were demolished including all mechanical, HVAC, plumbing electrical, and pavement. The areas were assessed and abated for any asbestos or hazardous materials. Once demolished, the areas were cleared and seeded to restore the area to green space. In total, 38,000 cubic yards of concrete slab and foundation, as well as, 90,000 cubic yards of debris were removed and disposed of.

SCOPE OF WORK

  • Complete Demolition

  • Hazardous Material Abatement

  • Site Restoration

  • Equipment Salvage

  • Utility Disconnects

  • Concrete & Foundation Removal

  • Re-grade & Seeding

SELF-PERFORMED WORK

Demolition, Contract Management, Safety, Quality Control, Scheduling, & Environmental Protection

Defense Supply Center.jpg
IAP Design Build LLC Logo
bottom of page